Item 35 of the second round of central ecological and environmental protection inspection rectification tasks that Yuncheng City is responsible for has been rectified and passed the verification and acceptance. In accordance with the requirements of the "Central Ecological Environmental Protection Inspection and Rectification Work Methods" regarding the acceptance and cancellation of accounts, the rectification status of this task is now announced as follows:
1. Rectification tasks
The replacement ratio of steel production capacity is illegal and "released". The inspection and rectification plan requires that new steel projects in the province need to be reduced and replaced at a ratio of 1.25:1. The inspector found that among the 18 steel production capacity replacement projects approved for implementation in the province since 2017, only one project is planned to be reduced and replaced according to a ratio of 1.25:1, and the remaining projects are all replaced according to a ratio of 1.006:1 to 1.02:1. Corrective measures
(1) Strict capacity replacement policy. In strict accordance with the relevant requirements of the Ministry of Industry and Information Technology's "Implementation Measures for Production Capacity Replacement in the Steel Industry" (original Ministry of Industry and Information Technology [2021] No. 46), the replacement of production capacity in the steel industry in key areas for air pollution prevention and control will be reduced and the replacement ratio shall not be less than 1.5:1. , the replacement ratio in other areas is not less than 1.25:1. When the compliant production capacity obtained after completing substantive mergers and reorganizations is used for project construction, the replacement ratio in key areas of air pollution prevention and control can be no less than 1.25:1, and the replacement ratio in other areas can be no less than 1.1:1.
(2) Strict management of production capacity replacement projects. Comprehensively investigate the situation of steel production capacity replacement and project construction in the province, establish a problem ledger, implement comprehensive policies, classify and deal with immediate reforms, and strengthen the inspection and supervision of steel production capacity replacement projects. Strictly require cities to implement their main responsibilities. Steel capacity replacement projects must comply with relevant requirements such as safety, environmental protection, energy consumption, quality, land use, industrial policy, capacity replacement and filing, etc. Completed projects with incomplete procedures will immediately stop production for rectification, and projects under construction with incomplete procedures will Construction will be stopped immediately for rectification, and construction of the proposed project can begin only after the procedures for the proposed project are completed.
(3) Increase efforts to resolve excess steel production capacity. A plan for upgrading and upgrading restricted process equipment for steel companies will be formulated before the end of December 2021, and more than 1.5 million tons of crude steel production capacity will be reduced by the end of December 2023.
3. Completion of rectification
(1) The Provincial Department of Industry and Information Technology has formulated and promulgated the "Implementation Rules for Carrying out Capacity Replacement Work in the Steel Industry of Our Province", which stipulates matters and work procedures related to production capacity replacement, and clarifies the proportion of production capacity replacement.
(2) The Provincial Department of Industry and Information Technology comprehensively investigates the situation of steel production capacity replacement and project construction, establishes ledger management, and ensures the safety of steel enterprise production capacity replacement projects in relevant cities such as Jinzhong, Changzhi, Jincheng, Luliang, Linfen, and Yuncheng , environmental protection, energy consumption, quality, land use, industrial policy, production capacity replacement and registration and other related procedures; projects under construction shall not start construction without complete procedures, and completed projects shall not be put into production without complete procedures. After investigation, our province currently has 8 completed projects and 4 projects under construction with complete procedures, and 6 proposed projects have completed partial procedures and will start construction after the procedures are completed.
(3) Since 2021, 5 capacity replacement projects have been promoted to be completed and put into operation, and the replacement of 6.51 million tons of iron-making capacity and 8.5 million tons of steel-making capacity has been completed. The crude steel production capacity has dropped from 73.8 million tons in 2020 to June 2023. 72.25 million tons, reducing crude steel production capacity by 1.55 million tons in total. Conducted acceptance checks on capacity replacement projects in Jincheng, Linfen and Yuncheng. The "Implementation Plan for Upgrading and Transforming Restricted Process Equipment in Shanxi Steel Industry" was issued to improve the level of process equipment in the steel industry and promote high-quality development of the steel industry.
If you have any objections to the public announcement of this task rectification, please provide feedback to the Shanxi Provincial Department of Ecology and Environment during the public announcement period (September 11, 2023 to September 20, 2023, a total of 10 days).
Contact person: Zhang Xiaobo
Landline: 0359-2628200
Email: ychbdc 163.com
September 11, 2023