On July 24, the start-up of the domestic butadiene rubber plant was generally stable, and the butadiene rubber plant of Qixiang Tengda was restarted on the 17th; the restart of the butadiene rubber plant of Yangzi Petrochemical was postponed; The petrochemical shunting plant was shut down for maintenance for about two weeks on July 18. The supply pressure of butadiene rubber increased slightly compared with the previous period.
butadiene rubber company | Equipment capacity (10,000 tons/year) | start |
Yantai Haopu | 6 | Run normally |
Shandong Wanda | 5 | Run normally |
Qixiang Tengda | 9 | Run normally |
Qilu Petrochemical | 7 | Run normally |
Sichuan Petrochemical | 15 | Three-line operation |
Maoming Petrochemical | 10 | Two-line operation |
Yanshan Petrochemical | 12+3 | High-load operation of high-cis-butadiene plant |
Yangzi Petrochemical | 10 | Parking |
Shengyu Chemical Industry | 8 | Two-line operation |
Taiwan Oaks Department | 7.2 | Run normally |
Dushanzi Petrochemical | 3 | Run at full capacity |
Xinjiang Lande | 5 | Run normally |
Daqing Petrochemical | 16 | Parking for maintenance |
Liaoning Shengyou | 3 | Parking |
Jinzhou Petrochemical | 3 | Run normally |
Zhejiang Transfar | 10+5 | Run normally |
Zhenhua Petrochemical | 10 | Run normally |
Shandong Yihua | 10 | Run normally |
Zhejiang Petrochemical | 10 | Parking for maintenance |