On May 29th, the butadiene rubber plant was started.
butadiene rubber company | Equipment capacity (10,000 tons/year) | start |
Yantai Haopu | 6 | Run normally after reboot on May 12th |
Shandong Wanda | 5 | Run normally |
Qixiang Tengda | 9 | Three-line operation |
Qilu Petrochemical | 7 | Run normally |
Sichuan Petrochemical | 15 | Three-line operation |
Maoming Petrochemical | 10 | 60% load operation |
Yanshan Petrochemical | 12+3 | Gao Shun Shun Ding plant will stop on the 15th |
Yangzi Petrochemical | 10 | Parking |
Shengyu Chemical Industry | 8 | Line-line operation |
Taiwan Oaks Department | 7.2 | Run normally |
Dushanzi Petrochemical | 3 | Run at full capacity |
Xinjiang Lande | 5 | Running normally after reboot on May 22 |
Daqing Petrochemical | 16 | 80% load operation |
Liaoning Shengyou | 3 | Parking |
Jinzhou Petrochemical | 3 | Line-line operation |
Zhejiang Transfar | 10+5 | Run normally |
Zhenhua Petrochemical | 10 | Restart on May 23 |
Shandong Yihua | 10 | Parking |
Zhejiang Petrochemical | 10 | Test run production BR 9000 |