On April 4th, the 10KV substation and distribution room in the third area of the BDO device of the Inner Mongolia Huaheng New Material Project undertaken by China Chemical 13th Chemical Construction Co., Ltd.
It is understood that the project is divided into three sets of BDO devices. Each BDO device area has an independent power transformation and distribution room. Each power transformation and distribution room has four dry-type transformers, two-stage high-voltage cabinets, and four-stage low-voltage cabinets. , a set of DC system, a set of EPS system.
Before receiving power, the project department actively organizes safety personnel to strictly control the power receiving area, conducts technical disclosures with on-site operators, arranges commissioning and power receiving personnel to conduct detailed inspections of the power distribution room, and arranges special personnel to check the sanitation of the power distribution room Clean up. With the joint efforts of the project management personnel and the on-site electrical construction personnel, and through the verification of the owner unit, the supervisory unit and the general contractor unit, the 10KV substation and distribution room in the three areas of the BDO device has successfully received power at one time.
At present, the equipment in the substation and distribution room is running well, and the power supply is normal. The successful power receiving this time marks that the project has successfully broken through an important node, and provides a guarantee for the subsequent stand-alone trial operation.