On September 15, Ningxia Guanneng New Materials Project held a gasifier hoisting and swearing-in mobilization meeting. The swearing-in mobilization meeting proposed that we should work hard for 70 days and sprint towards the goal of putting into production on November 18 with a decisive attitude.
After nearly 200 days of hard work, by the end of August, GN New Materials Project had completed 90% of the total equipment foundation and structures, 85% of the total underground pipe network construction, 40% of the large equipment arrival, and the total project construction 78% of the target tasks have entered the final installation period.
The project adopts Beijing Qingchuang Jinhua Technology Co., Ltd.’s coal-water slurry water-cooled wall direct-connected waste boiler gasifier (Jinhua furnace 3.0) technology, two Jinhua furnace 3.0 (two open), gasification pressure 6.5MPaG, The total gas volume is 120,000Nm3/h (CO+H2), and bituminous coal is used for gasification. The waste boilers of two Jinhua furnaces (3.0) produce a total by-product of 10.0MPa high-pressure steam 48t/h. Designed by Saiding Engineering Co., Ltd., this project is expected to be completed and put into production by the end of 2023.
Project Overview
Ningxia Guanneng New Materials Project is an industrial upgrade chain extension project invested mainly by Ningxia Lingyun Group. Ningxia Guanneng New Material Technology Co., Ltd.’s NMP, PBT/PBAT, PTEMG and other polymer materials, biodegradable materials and upstream supporting industry chain projects were settled in Hongyazi Industrial Park, Pingluo County in April 2022. The project uses calcium carbide, Gray hydrogen and green hydrogen are used as basic raw materials to extend the production of new polymer materials such as BDO-PBT-NMP-spandex.
The project is constructed in three phases, with a total investment of 14.68 billion yuan. At present, the first phase of the estimated total investment of 3.56 billion yuan, with 272,000 tons of BDO and 100,000 tons of PBT, is under construction and is expected to be completed and put into production this year. The construction of the third phase of the project is expected to be completed in October 2025. The project uses advanced technology and equipment in the industry. It is expected that after the project is fully completed, it will produce 500,000 tons of key raw materials for new energy and new materials annually, and will also be extended to produce 120,000 tons of degradable plastics, 100,000 tons of electrolyte, and 300,000 tons of spandex. . It is expected that after the project is fully completed, it will achieve an annual output value of 23.8 billion yuan, profits and taxes of 5.3 billion yuan, and provide more than 2,000 local jobs.
Ningxia Lingyun Group signed a contract with the Pingluo County Government on April 28, 2022, and initiated the establishment of Ningxia Guanneng New Material Technology Co., Ltd. It will invest in the construction of “polymer, biodegradable materials and upstream supporting industry chain projects” in Pingluo County, mainly producing NMP, PBT/PBAT, PTMEG, spandex and other products. The estimated total investment of the project is 16.71 billion yuan, and the fixed investment is 15.91 billion yuan. Among them, the estimated fixed investment of the first-phase project is 5.46 billion yuan, the estimated fixed investment of the second-phase project is 8.5 billion yuan, and the total investment of the 400MW wind and solar power generation and 6×5000m3/h electrolyzed water hydrogen production projects is 1.95 billion yuan.
Judging from the official promotional materials, the project is jointly invested and constructed by Jinhaiyi (Hong Kong) International, Jiangsu Suneng Investment Group, and Ningxia Lingyun Group. Jinhaiyi provides BDO equipment, Jiangsu Suneng is responsible for sales or modification, and Ningxia Lingyun provides raw materials. Carbide, three parties join forces.