On August 1, 2023, the national new energy grid connection and consumption situation was released. The utilization rate of photovoltaic power generation in June reached 98.7%, Wind power 97.7%. The 13 provinces of Beijing, Tianjin, Heilongjiang, Shanghai, Jiangsu, Zhejiang, Anhui, Fujian, Jiangxi, Chongqing, Sichuan, Guangxi, and Hainan have reached 100% utilization rate of photovoltaics.
It is worth noting that in June, Tibet’s light abandonment rate was 22.8%, and the photovoltaic utilization rate was only 77.2%, and it was 75.5% from January to June .
The original text is as follows:
According to the "Notice of the National Energy Administration on Matters Concerning the Development and Construction of Wind Power and Photovoltaic Power Generation in 2021" (Guonengfaxinneng [2021] 25 No.), in order to guide the rational investment and orderly construction of new energy, the situation of new energy grid connection and consumption in each provincial region in June 2023 is announced as follows.