On August 11, at the construction site of Xinye Energy’s 200,000-ton/year BDO Phase II project located in the East Industrial Park of Wujiaqu Economic and Technological Development Zone, there were many tower cranes, and construction workers were installing steel structures Welding, which marks the completion of the civil foundation of the project. It is reported that the project plans to deliver and install the civil works in mid-September.
Zhu Jindui, head of the project management department of Xinye Energy, said that the overall design of the second phase of the BDO project construction and the procurement of process equipment have been completed. The power station and other auxiliary projects have been capped, and the civil engineering foundation of the main installation area is nearing completion, and the steel structure installation and equipment installation stage have fully entered.
Project Overview
Xinye Energy’s 200,000-ton/year BDO project is located in Wujiaqu City. The first phase of the 60,000-ton BDO project was completed and put into operation in 2019. The total investment of the second-phase 140,000-ton BDO project is 2 billion yuan, and the construction period is 18 months. After the project is fully completed, it can realize an annual output value of 2.2 billion yuan, a net profit of 700 million yuan, and solve more than 100 jobs.
The project includes calcium carbide storage and crushing, acetylene plant, formaldehyde plant, BYD plant, BDO plant,
PSA unit, sewage renovation (excluding reclaimed water reuse, concentrated brine, crystallization and salt separation unit), instrument air and nitrogen buffer tank area, tank area, sulfur recovery tail gas treatment facility renovation, waste acid regeneration, waste liquid incineration, refrigeration station , heat exchange station, loading and unloading station, circulating water station, foam station, torch, cabinet room, control room (reuse of old), power distribution room, lubrication room (three-stage filtration), and supporting pipelines, electrical (excluding 110KV total transformer expansion), instrument control, fire protection, water supply and drainage, telecommunications, analytical instruments, HVAC, external pipes and pipe galleries, roads, etc., including the connection with the original system and the transformation required for the connection.
In order to complete the construction of the second phase of the project on schedule with quality and quantity, the company has specially set up a construction team for the second phase of the project, which consists of 6 professional groups including safety and environmental protection, civil engineering, and technology. As the members of each group, the backbone will do a good job in project construction management such as design, safety, quality, progress and cost control.
“As of now, 70% of the overall design of the project has been completed; the procurement of key equipment such as formaldehyde absorption towers and formaldehyde reactors and long-term equipment has entered the final stage; construction business agreements such as acetylene torch, sulfur recovery transformation, and refrigeration unit engineering have been completed. This year, we will strive to complete more than 85% of the total project volume.” said Zhu Jindui, head of the new industrial energy project department.