On June 8, 2023, with the successful roll-out of the first high-efficiency photovoltaic module, the second-phase 4GW high-efficiency module project of Yidao Xinneng Zhangzhou Base was officially put into production.
Since the construction of the second phase of the Zhangzhou base project started in February this year, the civil engineering construction of the component workshop has been completed within 80 days, the mechanical and electrical installation has been completed within 60 days, and the installation and commissioning of the two production lines have been completed within 20 days. It took only 120 days The smooth off-line of the first component has been realized.
The Zhangzhou base has a total investment of 1.5 billion yuan. It is the only photovoltaic manufacturing enterprise in southern Fujian Province. After the completion of the second phase of the project, the high-efficiency module production capacity of the base will reach 7GW. After the two phases of the project are fully put into operation, the annual output value will reach about 12 billion yuan.