In the past few days, the construction progress of Shaanxi Coal Group Gansu Investment Co., Ltd.'s 600,000 tons/year degradable material project has been "hurricane". Before the start of construction at the end of March, the key energy evaluation procedures have been obtained, and the project has finally landed in Yumen City. This is the first major provincial project in Gansu Province to use the method of "project comprehensive physical examination-departmental coordination and promotion-conditional approval" to obtain the evaluation procedures, creating a precedent for speeding up project construction in the province.
Shaanxi Coal Group Gansu Investment Co., Ltd. plans to start construction of 600,000 tons of degradable materials per year at the end of March. To obtain energy evaluation procedures, the company needs to go through procedures such as public announcement of capacity replacement plans. It will take more than one year to complete, which restricts the start of the project .
Conditional approval, that is, the Provincial Development and Reform Commission issues an energy evaluation and approval reply for the project in accordance with normal procedures, and the project can start construction based on this. The approval reply is invalid, and the approval reply can be truly effective after the capacity replacement is completed.
"In response to this problem, the Provincial Development and Reform Commission proposed a solution to the simultaneous advancement of capacity replacement and other preliminary procedures. The company promised to complete the capacity replacement within a certain time limit, and the relevant departments agreed to simultaneously advance the project. Yang Zhaojun, director of the Yumen City Development and Reform Bureau, said that this move is a concentrated expression of the implementation of the "three grasps and three promotions" action at the provincial, city and county levels.
Shaanxi Coal Group Gansu Investment Co., Ltd.'s 600,000-ton/year degradable material project was announced for the first time on July 26, 2022, including 360,000 tons/year BDO device, 60,000 tons/year PBS device, 300,000 tons/year PBAT plant, 100,000 tons/year PBT plant, etc.
The total investment of the project is 26.3 billion yuan. After the project is put into production, it can realize an annual industrial added value of 7.1 billion yuan, profits and taxes of 4.5 billion yuan, and can drive 2,000 jobs.
Not only that, this project belongs to the whole industrial chain project of coal chemical industry, and aims to build the largest demonstration base for the coupled development of "new energy + green hydrogen + chemical industry" in the country, effectively solve the problem of difficult energy replacement in chemical projects, and promote the development of new energy and chemical materials. An important way of coordinated development, it is listed as a major project in Gansu Province in 2023.
Review of the 600,000 tons/year degradable material project progress of Shaanxi Coal Group Gansu Investment Co., Ltd.
On September 26, 2021, the Yumen Municipal Government of Jiuquan City, Gansu Province and Shaanxi Coal Industry Chemical Group signed a project investment framework agreement on the Shaanxi Coal Yumen New Energy and Degradable Materials Project.
In December 2021, the project will be approved.
On February 17, 2022, Yang Zhaoqian, Secretary of the Party Committee and Chairman of Shaanxi Coal Group, led a team to call on the Deputy Secretary and Governor of Gansu Provincial Party Committee on investment in Gansu Jiuquan New Energy Degradable Materials Carbon Neutral Industrial Park and the construction of a wind power base. Ren Zhenhe and other leaders.
On May 12, 2022, Song Shijie, assistant to the general manager of Shaanxi Coal Group, director of the Strategic Planning Committee, deputy secretary of the Yulin Chemical Party Committee, and chairman Song Shijie, and his party met with the deputy team leader of the special team for ensuring the implementation of major projects of Shaanxi Coal Group in Jiuquan City and secretary of the Yumen Municipal Party Committee Wang Chao presided over the convening of the Shaanxi Coal Group Jiuquan major project Yumen inspection and negotiation meeting.
On July 22, 2022, the Jiuquan Municipal Government and Shaanxi Coal Group Company held an investment contract signing ceremony. The three projects planned by Shaanxi Coal Group in Jiuquan this time include the carbon-neutral industrial park project for new energy degradable materials.
On July 26, 2022, Shaanxi Coal Group Gansu Investment Co., Ltd. Yumen New Energy Degradable Materials Carbon Neutral Industrial Park project was announced for the first time. The construction site is located in East Building Materials Chemical Industrial Park, Yumen City, Gansu Province. The construction content includes 360,000 tons/year BDO device, 60,000 tons/year PBS device, 300,000 tons/year PBAT device, 100,000 tons/year PBT device, 10000Nm3 /h electrolysis water hydrogen production device, and 400,000 tons/year acetylene raw material preparation device (calcium carbide method), 120,000 tons/year acetylene device, 25000Nm3/h acetylene raw material tail gas hydrogen production device, 750,000 tons/year formaldehyde device, etc. device etc.
At the end of March 2023, the project is scheduled to start.